Upcoming Construction Project on Main Street 2025-04-17

Location: Between Mechanic Street and the Moncton-Dieppe city limit
Date: Tuesday, April 22 to Wednesday, Aug. 20
Work details: Major infrastructure renewal project. Below is a tentative schedule, which may be subject to change:
- April 22 to 30: Installation of a storm sewer outfall at the Petitcodiac River, along with localized work on Main Street, including nighttime lane reductions and temporary closures/detours.
- April 22 until approx. June 30: Closure of the Riverfront Trail, from the Settlers Landing to the Running Room (300 Main St.), due to ongoing outfall construction.
- May 1 to 15: Installation of storm sewer pipes within the Chateau Moncton parking lot.
- May 5 to 15: Milling and paving of Main Street between Mechanic Street and King Street, and from the Chateau Moncton traffic signals to the Dieppe city limits. Lane reductions will be in effect.
- May 15 to July 11: Installation of storm sewer pipes along Main Street from the Chateau Moncton to King Street. Lane reductions will be in effect throughout this period.
- July 11 to Aug. 4: Upgrades to the intersection of Main Street and King Street and related utility work. This phase will require a full closure of the intersection for several days, followed by lane reductions.
- Aug. 4 to Aug. 20: Milling and paving of Main Street from King Street to the Chateau Moncton traffic signals. Lane reductions will be in place during this time.
In total, crews will install approximately 357 metres of new storm system, 277 metres of renewed sanitary lines, and complete repairs to the water system.
Traffic impact: Work will be carried out in phases, with each phase affecting both vehicle and pedestrian access differently. The City will issue public service announcements in advance of each new phase to keep residents and commuters informed.